New Parking Lot

New Parking Lot

Miller Paving started laying asphalt on the east lot (4th Ave) on November 4th. This is the first section of the parking lot to receive the new asphalt. The property has been broken into sections to accomplish the paving while still keeping some parking available for the commercial tenants. Next section to get paved will likely be the south side of the building from 3rd Ave through to 4th Ave, followed by the north side lot and finally the west side (3rd Ave) lot. We are at the mercy of the weather and the work load of Miller Paving but it is hoped that 100% of the lot will be paved within a week. We will have the line painters stripe each section after it is paved.